File #: Res.07-0492    Version: A Name: Change Order on contract for Lake Michigan Pathway - Phase II
Type: Resolution Status: Passed
File created: 11/6/2007 In control: City Attorney's Office
On agenda: Final action: 11/6/2007
Title: Change Order on contract for Lake Michigan Pathway - Phase II Resolved, that Change Order No. 6 on Contract 49-05 (K5-056), Lake Michigan Pathway - Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $9,293.50. Further resolved, that funding to defray the cost of this change order be appropriated from Account 987.908.5130, Asphalt Resurfacing. Fiscal Note: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 07-1331

Sponsor

Alderman Hart

 

Title

Change Order on contract for Lake Michigan Pathway - Phase II

 

 

Resolved, that Change Order No. 6 on Contract 49-05 (K5-056), Lake Michigan Pathway - Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $9,293.50.

 

Further resolved, that funding to defray the cost of this change order be appropriated from Account 987.908.5130, Asphalt Resurfacing.

 

 

Fiscal Note: Funds are available as herein delineated.