Subject: Consideration of Change Order No. 1 on Contract EqRa-001, 2026 Lead Service Line Replacement, Miller Pipeline (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in a decrease of $1,669,437.09, bringing the contract total to $16,933,416.91.
|