Subject: (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting a request for final payment on Contract 41-08 (K8-047), Professional Services - Festival Hall Awnings, Hartmann Design, Inc., consultant. (Res.09-1680)
Recommendation of the Public Works and Services Committee on 8-25-09, 9-08-09, 9-29-09 and 10-13-09: Defer
Recommendation of the Public Works and Services Committee on 10-27-09: That the study of the awning system at Festival Hall, as submitted by Hartmann Design, Inc., be adopted for the installation of metal awnings to match the existing roof.
Further recommends that the professional services provided by Hartmann Design, Inc. under Contract 41-08 (K8-047), Professional Services - Festival Hall Awnings, be accepted and final payment authorized for a total contract amount of $2,500.00.
Fiscal Note: The recommended matching awnings are estimated to cost $50,000.00, but will have a 20 year life expectancy. The contract was authorized under Resolution No. 08-0857, dated June 3, 2008.