Legislation Details

File #: 0537-26    Version: A Name: Subject: Consideration of Change Order No. 2 on Contract W-25-9, 2025 Water Main Replacement - Phase 3, Willkomm Excavating & Grading, Inc. (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in a decrease of $3,308.00
Type: Communication Status: In Committee
File created: 6/10/2026 In control: Waterworks Commission
On agenda: Final action:
Title: Subject: Consideration of Change Order No. 2 on Contract W-25-9, 2025 Water Main Replacement - Phase 3, Willkomm Excavating & Grading, Inc. (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in a decrease of $3,308.00, bringing the total contract amount to $506,309.40.
Attachments: 1. 2026.06.17 - W-25-9 Change Order 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Subject: Consideration of Change Order No. 2 on Contract W-25-9, 2025 Water Main Replacement - Phase 3, Willkomm Excavating & Grading, Inc. (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in a decrease of $3,308.00, bringing the total contract amount to $506,309.40.