Sponsor
Alderman Helding
Title
Change Order No. 2 to Contract 39-10 (K0-048), Festival Hall Retaining Wall Repairs, Ricchio, Inc., contractor.
Resolved, that Change Order No. 2 on Contract 39-10 (K0-048), Festival Hall Retaining Wall Repair, Ricchio, Inc., contractor, be approved in the amount of $1,405.00.
Further recommends that funding to defray the cost of this change order be appropriated from Account 108.990.5010, Festival Hall-Retaining Wall Repairs.
Fiscal Note: Funds are available as herein delineated.