File #: 0044-26    Version: A Name: Subject: Consideration of Change Order No. 4 on Contract W-25-3 (rectifying), 2025 Water Main Replacement - Phase 2, Reesman's Excavating & Grading Inc. (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increas
Type: Communication Status: In Committee
File created: 1/14/2026 In control: Waterworks Commission
On agenda: Final action:
Title: Subject: Consideration of Change Order No. 4 on Contract W-25-3 (rectifying), 2025 Water Main Replacement - Phase 2, Reesman's Excavating & Grading Inc. (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $23,026.90, bringing the total contract amount to $1,265,270.30.
Attachments: 1. CO#4_W-25-3
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Subject: Consideration of Change Order No. 4 on Contract W-25-3 (rectifying), 2025 Water Main Replacement - Phase 2, Reesman's Excavating & Grading Inc. (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in an increase of $23,026.90, bringing the total contract amount to $1,265,270.30.