Change Order No. 1 on Contract 42-14 (K4-042), Pershing Park, Sam Meyers, LF #5 Reconstruction
Resolved, that Change Order No. 1 on Contract 42-14 (K4-042), Pershing Park, Sam Meyers, LF #5 Reconstruction, A.W. Oakes & Son, Inc., contractor, as submitted, is approved in the deduct amount of ($262,493.50).
Further resolved, that the funding accounts be adjusted by the following amounts:
($ 60,858.13) - Account 994.700.5060, Pershing Park Dr. Repaving
($ 38,380.56) - Account 106.991.5750, Surface Lot Repaving
($146,191.04) - Account 104.994.5460, Pershing / Meyers USEPA
($ 17,063.77) - Account 756.020.5590, Fund for Lake Michigan Grant
($262,493.50) - Total Deduct
Fiscal Note: Change Order No. 1 will result in a decrease in contract price.