Ricine Banner
File #: Res.08-0879    Version: A Name: Contract for 2008 Storm and Sanitary Sewer Lining
Type: Resolution Status: Passed
File created: 6/17/2008 In control: City Attorney's Office
On agenda: Final action: 6/17/2008
Title: Contract for 2008 Storm and Sanitary Sewer Lining Resolved, that Contract 32-08 (K8-036), 2008 Storm and Sanitary Sewer Lining, be awarded to Visu-Sewer Clean & Seal, Inc., Pewaukee, WI, at their bid price of $780,410.00, they being the lowest responsible bidder. Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts: $305,661.60 - Account 104.900.5410, Storm Sewer Repairs $ 43,150.00 - Account 287.988.5320, Sanitary MH, Misc. Locations $ 519.93 - Account 986.907.5310, San. Manholes, Reconstruction $ 72,621.64 - Account 987.907.5310, San. Sewer Construction $ 4,180.17 - Account 986.908.5320, San. Sewer Construction $354,276.66 - Account 287.988.5310, San. Sewer, Var. Loc. $780,410.00 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 08-2259

Sponsor

Alderman Helding

 

Title

Contract for 2008 Storm and Sanitary Sewer Lining

 

Resolved, that Contract 32-08 (K8-036), 2008 Storm and Sanitary Sewer Lining, be awarded to Visu-Sewer Clean & Seal, Inc., Pewaukee, WI, at their bid price of $780,410.00, they being the lowest responsible bidder.

 

Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:

 

$305,661.60 - Account 104.900.5410, Storm Sewer Repairs

$  43,150.00 - Account 287.988.5320, Sanitary MH, Misc. Locations

$        519.93 - Account 986.907.5310, San. Manholes, Reconstruction

$  72,621.64 - Account 987.907.5310, San. Sewer Construction

$    4,180.17 - Account 986.908.5320, San. Sewer Construction

$354,276.66 - Account 287.988.5310, San. Sewer, Var. Loc.

$780,410.00 - Total

 

 

Fiscal Note: Funds are available as herein delineated.