File #: Res.09-1599    Version: A Name: Change Order No. 1 on Contract 22-09 (K9-023), 2009 Alley Paving, A.W. Oakes & Son, contractor, be approved
Type: Resolution Status: Passed
File created: 9/15/2009 In control: City Attorney's Office
On agenda: Final action: 9/15/2009
Title: Change Order No. 1 on Contract 22-09 (K9-023), 2009 Alley Paving, A.W. Oakes & Son, contractor, be approved Resolved, that Change Order No. 1 on Contract 22-09 (K9-023), 2009 Alley Paving, A. W. Oakes & Son, contractor, be approved in the amount of $35,048.00. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $ 1,851.00 - Account 989.908.5530, Crosswalk Ramps $33,197.00 - Account 104.900.5420, Storm Sewers, Misc. $35,048.00 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 09-4100
Sponsor
Alderman Helding
 
Title
Change Order No. 1 on Contract 22-09 (K9-023), 2009 Alley Paving, A.W. Oakes & Son, contractor, be approved
 
Resolved, that Change Order No. 1 on Contract 22-09 (K9-023), 2009 Alley Paving, A. W. Oakes & Son, contractor, be approved in the amount of $35,048.00.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$  1,851.00 - Account 989.908.5530, Crosswalk Ramps
$33,197.00 - Account 104.900.5420, Storm Sewers, Misc.
$35,048.00 - Total
 
Fiscal Note: Funds are available as herein delineated.