Sponsor
Alderman Weidner
Title
Change Order No. 1 on Contract 06-13 (K3-006) - 2013 Concrete Street Reconstruction (R1), regarding the 5th Street boat launch
Resolved, that Change Order No. 1 on Contract 6-13 (K3-006), 2013 Concrete Street Reconstruction (R1), A.W. Oakes & Son, Inc., contractor, is approved in the amount of $58,600.00.
Fiscal Note: Funding to defray the cost of this change order be transferred from Account 993.700.5040, Pershing Park Boat Launch Lot Replacement, to Account 993.700.5110, Pershing Boat Launch Emergency Repair.