Ricine Banner
File #: Res.06-7297    Version: A Name: Change Order Lake Michigan Pathway, Phase II
Type: Resolution Status: Passed
File created: 11/8/2006 In control: City Attorney's Office
On agenda: Final action: 11/8/2006
Title: Change Order Lake Michigan Pathway, Phase II Resolved, that Change Order No. 3 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $85,731.96. Further Resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $25,000.00 - Account 104.986.5420, Storm Sewers, Various Locations $15,632.14 - Account 985.913.5090, Goold @ Michigan Slope Stabilization $ 6,417.06 - Account 985.913.5010, Environmental Remediation $30,848.42 - Account 985.908.5130, Asphalt Resurfacing $ 7,834.34 - Account 930.021.5810, CMAQ - Lake Michigan Pathway, Phase II $85,731.96 Fiscal Note: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-2738
Sponsor
Alderman Hart
 
Title
Change Order Lake Michigan Pathway, Phase II
 
Resolved, that Change Order No. 3 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $85,731.96.
 
Further Resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$25,000.00 - Account 104.986.5420, Storm Sewers, Various Locations
$15,632.14 - Account 985.913.5090, Goold @ Michigan Slope Stabilization
$  6,417.06 - Account 985.913.5010, Environmental Remediation
$30,848.42 - Account 985.908.5130, Asphalt Resurfacing
$  7,834.34 - Account 930.021.5810, CMAQ - Lake Michigan Pathway, Phase II
$85,731.96
 
Fiscal Note:  Funds are available as herein delineated.