Ricine Banner
File #: 07-1324    Version: A Name: Change Order No. 3 on Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit
Type: Communication Status: Passed
File created: 10/22/2007 In control: Public Works and Services Committee
On agenda: Final action: 11/6/2007
Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 3 on Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, K & L Construction, contractor. Recommendation: That Change Order No. 3 on Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, K & L Construction, contractor, as submitted, be approved in the amount of $29,650.00. Further recommends that funding to defray the cost of this change order be appropriated from Account 104.987.5420, Storm Sewers, Various Locations. Further recommends that the time to complete this contract be extended until November 1, 2007. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. Ald Hart - CO 3-39-06, 2. CO #3-39-06
Related files: Res.07-0491

Title

Subject:  Direct Referral.  Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 3 on Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, K & L Construction, contractor.

 

Recommendation: That Change Order No. 3 on Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, K & L Construction, contractor, as submitted, be approved in the amount of $29,650.00.

 

Further recommends that funding to defray the cost of this change order be appropriated from Account 104.987.5420, Storm Sewers, Various Locations.

 

Further recommends that the time to complete this contract be extended until November 1, 2007.

 

Fiscal Note: Funds are available as herein delineated.