File #: Res.06-6969    Version: A Name: CHANGE ORDER NORTH BEACH BATHHOUSE
Type: Resolution Status: Passed
File created: 4/5/2006 In control: City Attorney's Office
On agenda: Final action: 4/5/2006
Title: CHANGE ORDER NORTH BEACH BATHHOUSE RESOLVED, that Change Order #1 on Contract 51-05 (K5-058), Rubblestone Wall Replacement at North Beach Bathhouse, Bukacek Construction LLC, contractor, be approved for an increase of $795.00 and that final payment be approved for a total contract amount of $125,668.00. FISCAL NOTE: Funds are available in account #985.700.5070 - North Beach Wall.
Sponsors: David L. Maack

Sponsor

Alderman Maack

 

Title

CHANGE ORDER NORTH BEACH BATHHOUSE

 

RESOLVED, that Change Order #1 on Contract 51-05 (K5-058), Rubblestone Wall Replacement at North Beach Bathhouse, Bukacek Construction LLC, contractor, be approved for an increase of $795.00 and that final payment be approved for a total contract amount of $125,668.00.

 

 

FISCAL NOTEFunds are available in account #985.700.5070 - North Beach Wall.