File #:
|
Res.09-1754
Version:
A
|
Name:
|
Change Order No. 2 on Contract 22-09 (K9-023), 2009 Alley Paving, A.W. Oakes & Son, be approved
|
Type:
|
Resolution
|
Status:
|
Passed
|
On agenda:
|
|
Final action:
|
12/15/2009
|
Title:
|
Change Order No. 2 on Contract 22-09 (K9-023), 2009 Alley Paving, A.W. Oakes & Son, be approved
Resolved, that Change Order No. 2 on Contract 22-09 (K9-023), 2009 Alley Paving, A. W. Oakes & Son, Inc., contractor, be approved in the amount of $14,003.29.
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
$10,000.00 - Account 989.908.5030, Concrete Alley Paving
$ 4,003.29 - Account 104.900.5420, Storm Sewers, Misc.
$14,003.29 - Total
Fiscal Note: Funds are available as herein delineated.
|
Sponsor
Alderman Helding
Title
Change Order No. 2 on Contract 22-09 (K9-023), 2009 Alley Paving, A.W. Oakes & Son, be approved
Resolved, that Change Order No. 2 on Contract 22-09 (K9-023), 2009 Alley Paving, A. W. Oakes & Son, Inc., contractor, be approved in the amount of $14,003.29.
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
$10,000.00 - Account 989.908.5030, Concrete Alley Paving
$ 4,003.29 - Account 104.900.5420, Storm Sewers, Misc.
$14,003.29 - Total
Fiscal Note: Funds are available as herein delineated.
|