Subject: (Direct Referral) Change Order No. 1 on Contract 29-14 (K4-029) City Hall Annex - Boiler Replacement, Core Mechanical, Inc., contractor. (Res No. 15-0204)
Recommendation of the Public Works and Services Committee on 04-28-15: Deferred
Recommendation of the Public Works and Services Committee meeting on 05-12-15: That Change Order No. 1 on Contract 29-14 (K4-029), City Hall Annex - Boiler Replacement, Core Mechanical, Inc., contractor, as submitted, be approved in the amount of $4,395.00.
Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 45040-57200, Annex-Boiler Replacement.