Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 1 on Contract 2-09 (K9-002), 2009 Parking Ramp Maintenance, SPS Infrastructure, Inc., contractor. (Res.09-1499)
Recommendation of the Public Works and Services Committee on 6-30-09: That Change Order No. 1 on Contract 2-09 (K9-002), 2009 Parking Ramp Maintenance, SPS Infrastructure, Inc., contractor, be approved in the amount of $7,220.34.
Further recommends that funding to defray the cost of this change order be appropriated from Account 106.989.5760, Building Improvements-Ramps.
Fiscal Note: Funds are available as herein delineated.