File #: Res.06-6518    Version: A Name: CHANGE ORDER AND FINAL PAYMENT FOR REPLACING BARN AT WUSTUM MUSEUM
Type: Resolution Status: Passed
File created: 1/16/2006 In control: City Attorney's Office
On agenda: 1/17/2006 Final action: 1/17/2006
Title: CHANGE ORDER AND FINAL PAYMENT FOR REPLACING BARN AT WUSTUM MUSEUM

Sponsor

Alderman Maack

 

Title

CHANGE ORDER AND FINAL PAYMENT FOR REPLACING BARN AT WUSTUM MUSEUM

 

Body

RESOLVED, that Change Order No. 1 on Contract 48-05 (K5-055), for services to Replace Barn at Wustum Museum, be approved in the increased amount of $9,438.00 and that funds to cover the cost of this change order be appropriated from Account 655.000.5960, Wustum Renovate Barn.

 

FURTHER RESOLVED, that the work of Absolute Contraction Enterprises be accepted and final payment made in the amount of $70,138.00.

 

 

Fiscal Note

Fiscal Note: This contract was approved by Resolution 6654 of September 6, 2005.