Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 1 to Contract 48-13 (K3-053), Boiler Replacement-City Hall Annex and Tyler Domer Center (R1). Martin Petersen Co., Inc., contractor. (Res. No. 14-0010)
Recommendation of the Public Works and Services Committee on 8-13-13, 8-27-13, 9-10-13 and 9-24-13: Defer
Recommendation of the Public Works and Services Committee on 01-14-14: That Change Order No. 1 on Contract 48-13 (K3-053), Boiler Replacement-City Hall Annex and Tyler Domer Center (R1), Martin Petersen Co., Inc., contractor, as submitted, be approved in the deduct amount of $302,743.00.
Further recommends that the funding accounts be adjusted by the following amount:
$3,077.00 - Account 993.670.5010, Tyler-Domer Boiler Replacement
($305,820.00) - Account 993.200.503, Annex - Boiler Replacement