Title: Change Order on 2008 Street Paving contract Resolved, that Change Order No. 1 to Contract 14-08 (K8-015), 2008 Street Paving, John's Concrete, Inc., contractor, be approved in the amount of $49,967.80. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $43,967.80 - Account 988.908.5010, Concrete Street Paving Miscellaneous Locations $ 6,000.00 - Account 287.988.5310, Sanitary Sewer Various Locations $49,967.80 - Total Further resolved, that a time extension until July 29, 2008 to complete this work be approved. Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 08-2481
Sponsor
Alderman Helding
 
Title
Change Order on 2008 Street Paving contract
 
Resolved, that Change Order No. 1 to Contract 14-08 (K8-015), 2008 Street Paving, John's Concrete, Inc., contractor, be approved in the amount of $49,967.80.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$43,967.80 - Account 988.908.5010, Concrete Street Paving Miscellaneous Locations
$  6,000.00 - Account 287.988.5310, Sanitary Sewer Various Locations
$49,967.80 - Total
 
Further resolved, that a time extension until July 29, 2008 to complete this work be approved.
 
Fiscal Note: Funds are available as herein delineated.