File #: Res.14-0320    Version: A Name: Change Order No. 1 to Contract 02-14 (K4-002), Boiler Replacement - St. Maintenance Garage
Type: Resolution Status: Passed
File created: 8/4/2014 In control: City Attorney's Office
On agenda: Final action: 8/4/2014
Title: Change Order No. 1 to Contract 02-14 (K4-002), Boiler Replacement - St. Maintenance Garage Resolved, that Change Order No. 1 to Contract 02-14 (K4-002), Boiler Replacement - St. Maintenance Garage, Southport Heating Plumbing Geothermal, contractor, is approved in the amount of $29,275.00. Fiscal Note: Funding to defray the cost of this change order be appropriated from Account 994.410.5010, Solid Waste Garage HVAC.
Sponsors: Jim Kaplan
Related files: 14-10406
Sponsor
Alderman Kaplan
 
Title
Change Order No. 1 to Contract 02-14 (K4-002), Boiler Replacement - St. Maintenance Garage
 
Resolved, that Change Order No. 1 to Contract 02-14 (K4-002), Boiler Replacement - St. Maintenance Garage, Southport Heating Plumbing Geothermal, contractor, is approved in the amount of $29,275.00.
 
Fiscal Note: Funding to defray the cost of this change order be appropriated from Account 994.410.5010, Solid Waste Garage HVAC.