Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 1 on Contract 52-09 (K9-053), Window Replacement-City Hall Annex, Softer Lite Window Company, contractor. (Res.09-1758)
Recommendation of the Public Works and Services Committee on 10-13-09, 10-27-09, 11-10-09 and 11-24-09: Defer
Recommendation of the Public Works and Services Committee on 12-8-09: That Change Order No. 1 on Contract 52-09 (K9-053), Window Replacement-City Hall Annex, Softer Lite Window Company, contractor, be approved in the amount of $12,330.00.
Further recommends that funding to defray the cost of this change order be appropriated from the following accounts:
$ 1,655.00 - Account 989.200.5020, Annex-Stairwell Windows
$10,675.00 - Account 987.210.5010, Safety Bldg Precast Panel Repl
$12,330.00 - Total
Fiscal Note: Funds are available as herein delineated.