Title:
|
Subject: Consideration of Change Order No. 1 (rectifying) on Contract W-24-2, 2024 Pavement Restoration, Conventional Concrete (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in an decrease of $61,436.77, bringing the contract total to $339,988.23.
|