File #: 0057-26    Version: A Name: Subject: Consideration of Change Order No. 1 (rectifying) on Contract W-24-2, 2024 Pavement Restoration, Conventional Concrete Systems (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an decrease of $61,436.77, b
Type: Communication Status: Passed
File created: 1/15/2026 In control: Waterworks Commission
On agenda: Final action: 1/21/2026
Title: Subject: Consideration of Change Order No. 1 (rectifying) on Contract W-24-2, 2024 Pavement Restoration, Conventional Concrete Systems (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an decrease of $61,436.77, bringing the contract total to $339,988.23.
Attachments: 1. CO#1_W-24-2

Title

Subject: Consideration of Change Order No. 1 (rectifying) on Contract W-24-2, 2024 Pavement Restoration, Conventional Concrete Systems (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in an decrease of $61,436.77, bringing the contract total to $339,988.23.