File #: 0705-23    Version: A Name: Subject: Change Order No. 2 on Contract W-22-4, Water Main Replacement - Phase 3, Five Star Energy Services (Contractor) Recommendation: To Approve Fiscal Note: Contract change results in a net credit reduction of ($3,557.00), bringing the total con
Type: Communication Status: Passed
File created: 7/11/2023 In control: Waterworks Commission
On agenda: Final action: 9/19/2023
Title: Subject: Change Order No. 2 on Contract W-22-4, Water Main Replacement - Phase 3, Five Star Energy Services (Contractor) Recommendation: To Approve Fiscal Note: Contract change results in a net credit reduction of ($3,557.00), bringing the total contract amount to $808,096.98.
Attachments: 1. w-22-4_co#2

Title

Subject: Change Order No. 2 on Contract W-22-4, Water Main Replacement - Phase 3, Five Star Energy Services (Contractor)

 

Recommendation: To Approve

 

Fiscal Note: Contract change results in a net credit reduction of ($3,557.00), bringing the total contract amount to $808,096.98.