Ricine Banner
File #: 10-4829    Version: A Name: Change Order No. 1 on Contract 58-09 (K9-059), 2009 LED Street Lights, CDBG-R
Type: Communication Status: Passed
File created: 3/4/2010 In control: Public Works and Services Committee
On agenda: Final action: 3/16/2010
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 1 on Contract 58-09 (K9-059), 2009 LED Street Lights, CDBG-R, Ruud Lighting, contractor. (Res.10-1920) Recommendation of the Public Works and Services Committee on 3-9-10: That Change Order No. 1 on Contract 58-09 (K9-059), 2009 LED Street Lights, CDBG-R, Ruud Lighting, contractor, be approved in the amount of $109,112.00. Further recommends that funding to defray the cost of this change order be appropriated from Account 806.030.5620, Street Light Retrofit. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. Ald Helding - CO 1-58-09, 2. CO #1-58-09 Short Form
Related files: Res.10-1920
Title
Subject: (Direct Referral)  Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 1 on Contract 58-09 (K9-059), 2009 LED Street Lights, CDBG-R, Ruud Lighting, contractor.  (Res.10-1920)
 
Recommendation of the Public Works and Services Committee on 3-9-10: That Change Order No. 1 on Contract 58-09 (K9-059), 2009 LED Street Lights, CDBG-R, Ruud Lighting, contractor, be approved in the amount of $109,112.00.
 
Further recommends that funding to defray the cost of this change order be appropriated from Account 806.030.5620, Street Light Retrofit.
 
Fiscal Note: Funds are available as herein delineated.