Ricine Banner
File #: 10-5891    Version: A Name: Change Order No. 2 to Contract 17-10 (K0-017), State Street Bridge Repairs. Zenith Tech, Inc., contractor.
Type: Communication Status: Passed
File created: 12/9/2010 In control: Public Works and Services Committee
On agenda: Final action: 12/21/2010
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 to Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor. (Res.10-2345) Recommendation of the Public Works and Services Committee on 1-12-10: That Change Order No. 2 on Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor, be approved in the amount of $44,075.00. Further recommends that funding to defray the cost of this change order be appropriated from Account 930.077.5810, State Street Lift Bridge Repairs. Fiscal Note: Funds are available as herein delineated and are fully reimbursable by the State of Wisconsin.
Attachments: 1. 17-10 CO #2.pdf, 2. 17-10 CO #2 memo.pdf
Related files: Res.10-2345
Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 to Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor.  (Res.10-2345)
 
Recommendation of the Public Works and Services Committee on 1-12-10: That Change Order No. 2 on Contract 17-10 (K0-017), State Street Bridge Repairs, Zenith Tech, Inc., contractor, be approved in the amount of $44,075.00.
 
Further recommends that funding to defray the cost of this change order be appropriated from Account 930.077.5810, State Street Lift Bridge Repairs.
 
Fiscal Note: Funds are available as herein delineated and are fully reimbursable by the State of Wisconsin.