File #: 1055-26    Version: A Name: Subject: Consideration of Change Order No. 2 on Contract EqRa-001, Equiflow Lead Service Line Replacement, Miller Pipeline (Contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $425,610.24, bringing the
Type: Communication Status: Passed
File created: 11/12/2026 In control: Common Council
On agenda: Final action: 11/18/2026
Title: Subject: Consideration of Change Order No. 2 on Contract EqRa-001, Equiflow Lead Service Line Replacement, Miller Pipeline (Contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $425,610.24, bringing the contract total to $17,359,027.15.
Attachments: 1. 2026.11.18 - Waterworks Change Order Memo - EqRa-001 CO#2

Title

Subject: Consideration of Change Order No. 2 on Contract EqRa-001, Equiflow Lead Service Line Replacement, Miller Pipeline (Contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in an increase of $425,610.24, bringing the contract total to $17,359,027.15.