Change Order No. 1 to Contract 7-13 (K3-007), Johnson Park Streambank Stabilization Project
Resolved, that Change Order No. 1 on Contract 7-13 (K3-007), Johnson Park Streambank Stabilization Project, Native Construction & Landscaping, contractor, is approved in the amount of $22,608.00.
Fiscal Note: Funding to defray the cost of this change order be appropriated from the following accounts:
$20,778.00 - Account 104.992.5470, Lincoln Park Streambank Stabilization
$ 1,830.00 - Account 107.000.5750, Land Improvement
$22,608.00 - Total