File #: 15-00174    Version: A Name: Change Order No. 1 on Contract 38-14 (K4-038), 2014 City Resurfacing Phase ll (R1), Payne & Dolan, Inc., contractor. (Res. No. 15-0089)
Type: Communication Status: Passed
File created: 2/20/2015 In control: Public Works and Services Committee
On agenda: Final action: 3/2/2015
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/City Engineer submitting Change Order No. 1 on Contract 38-14 (K4-038), 2014 City Resurfacing Phase ll (R1), Payne & Dolan, Inc., contractor. (Res. No. 15-0089) Recommendation of the Public Works and Services Committee on 02-24-15: That Change Order No. 1 on Contract 38-14 (K4-038), 2014 City Resurfacing Phase ll (R1), Payne & Dolan, Inc., contractor, as submitted, be approved in the amount of $5,850.20. Further recommends that funding to defray the cost of the change order be appropriated from Acct 994.908.5220 (Org-Object 45040-57500, Asphalt Resurfacing) in the amount of $5,850.20. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 15-00174 CO1 Contract 38-14
Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/City Engineer submitting Change Order No. 1 on Contract 38-14 (K4-038), 2014 City Resurfacing Phase ll (R1), Payne & Dolan, Inc., contractor. (Res. No. 15-0089)
 
Recommendation of the Public Works and Services Committee on 02-24-15: That Change Order No. 1 on Contract 38-14 (K4-038), 2014 City Resurfacing Phase ll (R1), Payne & Dolan, Inc., contractor, as submitted, be approved in the amount of $5,850.20.
 
Further recommends that funding to defray the cost of the change order be appropriated from Acct 994.908.5220 (Org-Object 45040-57500, Asphalt Resurfacing) in the amount of $5,850.20.
 
Fiscal Note: Funds are available as herein delineated.