Ricine Banner
File #: 11-6047    Version: A Name: Change Order No. 2 to Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1).
Type: Communication Status: Passed
File created: 2/1/2011 In control: Public Works and Services Committee
On agenda: Final action: 2/16/2011
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 to Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1), AZAR LLC, contractor. (Res.11-2415) Recommendation of the Public Works and Services Committee on 2-8-11: That Change Order No. 2 on Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1), AZAR LLC, contractor, be approved in the amount of $821.40. Further recommends that funding to defray the cost of this change order be appropriated from Account 108.990.5510, Memorial Hall Tuckpointing. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 34-10 CO #2.pdf
Related files: Res.11-2415
Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 to Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1), AZAR LLC, contractor.  (Res.11-2415)
 
Recommendation of the Public Works and Services Committee on 2-8-11: That Change Order No. 2 on Contract 34-10 (K0-042), City Hall and Memorial Hall Restoration (R1), AZAR LLC, contractor, be approved in the amount of $821.40.
 
Further recommends that funding to defray the cost of this change order be appropriated from Account 108.990.5510, Memorial Hall Tuckpointing.
 
Fiscal Note: Funds are available as herein delineated.