Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 1 to Contract 22-12 (K2-023), Safety Building-Replace Ceiling and Lights, Absolute Construction Company, contractor. (Res. No. 12-3233)
Recommendation of the Public Works and Services Committee on 7-10-12: That Change Order No. 1 on Contract 22-12 (K2-023), Safety Building-Replace Ceiling and Lights, Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $20,391.00.
Fiscal Note: Funding to defray the cost of this change order be appropriated from Account 991.210.5040, Safety Building-Building Updates.