Title: Change Order No. 2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays Resolved, that Change Order No.2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays, A. W. Oakes & Son, contractor, be approved, in the credit amount of $5,400.00. Further resolved, that the completion date be extended to December 3, 2008. Fiscal Note: The contract amount was decreased due to the withholding of liquidated damages for completing the project after the original completion date of November 5, 2008.
Sponsors: Gregory Helding
Related files: 08-2910
Sponsor
Alderman Helding
 
Title
Change Order No. 2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays
 
Resolved, that Change Order No.2 on Contract 44-08 (K8-052), 2008 Sanitary Sewer Relays, A. W. Oakes & Son, contractor, be approved, in the credit amount of $5,400.00.
 
Further resolved, that the completion date be extended to December 3, 2008.
 
Fiscal Note: The contract amount was decreased due to the withholding of liquidated damages for completing the project after the original completion date of November 5, 2008.