File #: Res.08-0844    Version: A Name: Final payment on contract for Concrete Street Reconstruction, LaLonde Contractors
Type: Resolution Status: Passed
File created: 6/3/2008 In control: City Attorney's Office
On agenda: Final action: 6/3/2008
Title: Final payment on contract for Concrete Street Reconstruction, LaLonde Contractors Resolved, that the work of LaLonde Contractors, Inc., under Contract 25-07 (K7-029), Concrete Street Reconstruction, be accepted and final payment authorized for a total contract amount of $2,150,366.14, from funds heretofore appropriated. Fiscal Note: Contract was authorized under Resolution No. 07-0218, dated May 15, 2007.
Sponsors: Gregory Helding
Related files: 08-2189
Sponsor
Alderman Helding
 
Title
Final payment on contract for Concrete Street Reconstruction, LaLonde Contractors
 
Resolved, that the work of LaLonde Contractors, Inc., under Contract 25-07 (K7-029), Concrete Street Reconstruction, be accepted and final payment authorized for a total contract amount of $2,150,366.14, from funds heretofore appropriated.
 
Fiscal Note: Contract was authorized under Resolution No. 07-0218, dated May 15, 2007.