File #: Res.07-0331    Version: A Name: Change Order Curb and Gutter Repair
Type: Resolution Status: Passed
File created: 7/17/2007 In control: City Attorney's Office
On agenda: Final action: 7/17/2007
Title: Change Order Curb and Gutter Repair Resolved, that Change Order No. 1 on Contract 16-07 (K7-019), Curb and Gutter Repair, C.D.B.G., D.C. Burbach, Inc., contractor, as submitted, be approved in the amount of $11,632.18. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $ 5,074.60 - Account 897.030.5510, Curb & Gutter Repair CDBG $ 4,475.00 - Account 104.987.5420, Storm Sewer $ 2,082.58 - Account Concrete Paving, Misc. Locations $11,632.18 Fiscal Note: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 07-0865

Sponsor

Alderman Hart

 

Title

Change Order Curb and Gutter Repair

 

 

Resolved, that Change Order No. 1 on Contract 16-07 (K7-019), Curb and Gutter Repair, C.D.B.G., D.C. Burbach, Inc., contractor, as submitted, be approved in the amount of $11,632.18.

 

Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:

 

$  5,074.60 - Account 897.030.5510, Curb & Gutter Repair CDBG

$  4,475.00 - Account 104.987.5420, Storm Sewer

$  2,082.58 - Account Concrete Paving, Misc. Locations

$11,632.18

 

Fiscal Note: Funds are available as herein delineated.