Ricine Banner
File #: 09-4617    Version: A Name: Final payment on Contract 3-07 (K7-003), Professional Services - Central Heating Plant Repairs, HNTB, consultant.
Type: Communication Status: Passed
File created: 1/6/2010 In control: Public Works and Services Committee
On agenda: Final action: 1/19/2010
Title: Subject: (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting a request for final payment on Contract 3-07 (K7-003), Professional Services - Central Heating Plant Repairs, HNTB, consultant. (Res.10-1803) Recommendation of the Public Works and Services Committee on 1-12-10: The professional services provided by HNTB under Contract 3-07 (K7-003), Professional Services - Central Heating Plant Repairs, be accepted and final payment authorized for a total contract amount of $29,346.88. Fiscal Note: Contract was authorized under Resolution No. 06-7358, dated December 19, 2006.
Attachments: 1. 03-07 FPR.pdf
Related files: Res.10-1803
Title
Subject: (Direct Referral) Communication from the Commissioner of Public Works/City Engineer submitting a request for final payment on Contract 3-07 (K7-003), Professional Services - Central Heating Plant Repairs, HNTB, consultant.  (Res.10-1803)
 
Recommendation of the Public Works and Services Committee on 1-12-10: The professional services provided by HNTB under Contract 3-07 (K7-003), Professional Services - Central Heating Plant Repairs, be accepted and final payment authorized for a total contract amount of $29,346.88.
 
Fiscal Note: Contract was authorized under Resolution No. 06-7358, dated December 19, 2006.