File #: Res.06-7065    Version: A Name: FINAL PAYMENT FOR CURB & GUTTER REPLACEMENT CDBG
Type: Resolution Status: Passed
File created: 6/6/2006 In control: City Attorney's Office
On agenda: Final action: 6/6/2006
Title: FINAL PAYMENT FOR CURB & GUTTER REPLACEMENT CDBG RESOLVED, that the work of J.B. Construction Company, under Contract 37-05 (K5-044), Curb & Gutter Replacement, CDBG, be accepted and final payment authorized for a total contract amount of $128,000.77. FISCAL NOTE: Contract was authorized under Resolution No. 6576 of July 19, 2005.
Sponsors: Ronald Hart
Related files: 06-1975
Sponsor
Alderman Hart
 
Title
FINAL PAYMENT FOR CURB & GUTTER REPLACEMENT CDBG
 
 
RESOLVED, that the work of J.B. Construction Company, under Contract 37-05 (K5-044), Curb & Gutter Replacement, CDBG, be accepted and final payment authorized for a total contract amount of $128,000.77.
 
 
FISCAL NOTE:  Contract was authorized under Resolution No. 6576 of July 19, 2005.