Title:
|
Subject: Communication Sponsored by Alder Harmon, on behalf of the Waterworks Commission, requesting approval of a resolution regarding declaration of official intent to reimburse costs attributed to 2026 Water Main Replacement Project.
Recommendation of the Waterworks Commission on 06/18/25: To Approve with a Referral to the Finance & Personnel Committee.
Staff Recommendation: That the Waterworks Commission request for approval of a resolution regarding declaration of official intent to reimburse costs attributed to the 2026 Water Main Replacement Project be approved.
Fiscal Note: The aggregate principal amount of debt for the project is expected not to exceed $10,000,000.00, with the balance reduced by eligible Principal Forgiveness earned. Funding for the Project to be financed through the FY 2026 WDNR Safe Drinking Water Loan Program.
|