File #: Res.06-7295    Version: A Name: Change Order Curb and Gutter Repair, Contract 31-06-(K6-032)
Type: Resolution Status: Passed
File created: 11/8/2006 In control: City Attorney's Office
On agenda: Final action: 11/8/2006
Title: Change Order Curb and Gutter Repair, Contract 31-06-(K6-032) Resolved, that Change Order No. 1 on Contract 31-06 (K6-032), Curb and Gutter Repair D.C. Burbach, Inc., contractor, as submitted, be approved in the amount of $10,213.99. Further Resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $ 5,907.33 - Account 985.908.5220, Curb and Gutter Replacement $ 4,306.66 - Account 986.908.5220, Curb and Gutter Replacement $10,213.99 Fiscal Note: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-2727
Sponsor
Alderman Hart
 
Title
Change Order Curb and Gutter Repair, Contract 31-06-(K6-032)
 
Resolved, that Change Order No. 1 on Contract 31-06 (K6-032), Curb and Gutter Repair D.C. Burbach, Inc., contractor, as submitted, be approved in the amount of $10,213.99.
 
Further Resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$  5,907.33 - Account 985.908.5220, Curb and Gutter Replacement
$  4,306.66 - Account 986.908.5220, Curb and Gutter Replacement
$10,213.99
 
Fiscal Note:  Funds are available as herein delineated.