Title: CONTRACT FOR PRITCHARD/RESERVOIR PARK POND RETROFIT RESOLVED, that Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, be awarded to K&L Construction, Inc., Whitelaw, WI, at its bid price of $376,336.80, it being the lowest responsible bidder. FURTHER RESOLVED, that funding to defray the cost of this public works project be appropriated from the following accounts: $ 77,000.00 - Account 104.986.5520, Highridge Pond Retrofit $ 77,000.00 - Account 104.986.5530, Pritchard Pond Retrofit $222,336.80 - Account 104.985.5420, Storm Sewers, Various Locations $376,336.80 - Total FISCAL NOTE: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-2415

Sponsor

Alderman Hart

 

Title

CONTRACT FOR PRITCHARD/RESERVOIR PARK POND RETROFIT

 

 

RESOLVED, that Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, be awarded to K&L Construction, Inc., Whitelaw, WI, at its bid price of $376,336.80, it being the lowest responsible bidder.

 

FURTHER RESOLVED, that funding to defray the cost of this public works project be appropriated from the following accounts:

 

$  77,000.00 - Account 104.986.5520, Highridge Pond Retrofit

$  77,000.00 - Account 104.986.5530, Pritchard Pond Retrofit

$222,336.80 - Account 104.985.5420, Storm Sewers, Various Locations

$376,336.80 - Total

 

 