Sponsor
Alderman Hart
Title
CONTRACT FOR PRITCHARD/RESERVOIR PARK POND RETROFIT
RESOLVED, that Contract 39-06 (K6-041), Pritchard/Reservoir Park Pond Retrofit, be awarded to K&L Construction, Inc., Whitelaw, WI, at its bid price of $376,336.80, it being the lowest responsible bidder.
FURTHER RESOLVED, that funding to defray the cost of this public works project be appropriated from the following accounts:
$ 77,000.00 - Account 104.986.5520, Highridge Pond Retrofit
$ 77,000.00 - Account 104.986.5530, Pritchard Pond Retrofit
$222,336.80 - Account 104.985.5420, Storm Sewers, Various Locations
$376,336.80 - Total
FISCAL NOTE: Funds are available as herein delineated.