File #: Res.09-1595    Version: A Name: Contract 56-09 (K9-057), Safety Building - EIFS Cladding Project, be awarded to Camosy, Inc
Type: Resolution Status: Passed
File created: 9/15/2009 In control: City Attorney's Office
On agenda: Final action: 9/15/2009
Title: Contract 56-09 (K9-057), Safety Building - EIFS Cladding Project, be awarded to Camosy, Inc. Resolved, that Contract 56-09 (K9-057), Safety Building - EIFS Cladding Project, be awarded to Camosy, Inc., Zion, IL, at their bid price of $22,500.00 plus Alternative Bid #1 in the amount of $6,200.00, for a total contract amount of $28,700.00, it being the lowest responsible bidder. Further resolved, that funding to defray the cost of this public works project be appropriated from Account 987.210.5010, Safety Building Precast Panel Replacement. Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Attachments: 1. 56-09 Bid Tab.pdf, 2. 56-09 Bid Results.pdf
Related files: 09-4124
Sponsor
Alderman Helding
 
Title
Contract 56-09 (K9-057), Safety Building - EIFS Cladding Project, be awarded to Camosy, Inc.
 
Resolved, that Contract 56-09 (K9-057), Safety Building - EIFS Cladding Project, be awarded to Camosy, Inc., Zion, IL, at their bid price of $22,500.00 plus Alternative Bid #1 in the amount of $6,200.00, for a total contract amount of $28,700.00, it being the lowest responsible bidder.
 
Further resolved, that funding to defray the cost of this public works project be appropriated from Account 987.210.5010, Safety Building Precast Panel Replacement.
 
Fiscal Note:  Funds are available as herein delineated.