Legislation Details

File #: 0546-26    Version: A Name: Subject: Request for Final Payment (retainage) on Contract W-25-4, 2025 Lead Service Replacement, Miller Pipeline (contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-25-4 is complete at a final cost of $3,080,389.54.
Type: Communication Status: In Committee
File created: 6/10/2026 In control: Waterworks Commission
On agenda: Final action:
Title: Subject: Request for Final Payment (retainage) on Contract W-25-4, 2025 Lead Service Replacement, Miller Pipeline (contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-25-4 is complete at a final cost of $3,080,389.54.
Attachments: 1. 2026.06.17 - W-25-4 Final Payment
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Subject: Request for Final Payment (retainage) on Contract W-25-4, 2025 Lead Service Replacement, Miller Pipeline (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract W-25-4 is complete at a final cost of $3,080,389.54.