Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/City Engineer submitting Change Order No. 1 on Contract 17-14 (K4-017), Racine Streambank Stabilization, Native Construction, contractor. (Res. No. 14-0520)
Recommendation of the Public Works and Services Committee on December 9, 2014: That Change Order No. 1 on Contract 17-14 (K4-017), Racine Streambank Stabilization, Native Construction, contractor, as submitted, be approved in the amount of $117,268.23.
Further recommends that funding to defray the cost of this change order be appropriated from the following accounts:
$ 55,572.75 - Account 104.993.5430, Wash Pk Streambank A, UNP (Spring St.)
$ 61,695.48 - Account 104.993.5440, Wash Pk Streambank B, (Washington Pk)
$117,268.23 - Total
Fiscal Note: Funds are available as herein delineated.