Change Order No. 1 on Contract 9-09 (K9-009), 2009 Concrete Street Reconstruction (R1), LaLonde Contractors, be approved
Resolved, that Change Order No. 1 on Contract 9-09 (K9-009), 2009 Concrete Street Reconstruction (R1), LaLonde Contractors, contractor, be approved in the amount of $16,811.80.
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
$ 4,906.30 - Account 989.600.5010, Traffic Signal Replacements
$11,905.50 - Account 287.989.5310, Sanitary Sewer, Var. Loc.
$16,811.80 - Total