File #: 08-2831    Version: A Name: Accept a Focus on Energy Grant for the installation of LED light fixtures at the Civic Centre Parking Ramp, Phase III.
Type: Communication Status: Passed
File created: 10/22/2008 In control: Public Works and Services Committee
On agenda: Final action: 11/18/2008
Title: Subject: Communication from the Assistant Commissioner of Public Works/Operations requesting permission to accept a Focus on Energy Grant for the installation of LED light fixtures at the Civic Centre Parking Ramp, Phase III. (Res.08-1102) Recommendation of the Public Works and Services Committee on 11-11-08: That the Commissioner of Public Works/City Engineer be authorized and directed to enter into a grant agreement, on behalf of the City of Racine, with Focus on Energy which will provide $1,733.00 in funding for Phase III of the Civic Centre Parking Ramp LED Light Fixture project. The total estimated cost of this project is $18,450.00. Further recommends that funds for this project are available in Account 106.987.5120, Parking Ramp Improvements. Fiscal Note: The grant and resulting estimated reduction in annual energy costs of $2,100.00 will result in an 8 year return on investment.
Related files: Res.08-1102

Title

Subject: Communication from the Assistant Commissioner of Public Works/Operations requesting permission to accept a Focus on Energy Grant for the installation of LED light fixtures at the Civic Centre Parking Ramp, Phase III.  (Res.08-1102)

 

Recommendation of the Public Works and Services Committee on 11-11-08: That the Commissioner of Public Works/City Engineer be authorized and directed to enter into a grant agreement, on behalf of the City of Racine, with Focus on Energy which will provide $1,733.00 in funding for Phase III of the Civic Centre Parking Ramp LED Light Fixture project. The total estimated cost of this project is $18,450.00.

 

Further recommends that funds for this project are available in Account 106.987.5120, Parking Ramp Improvements.

 

Fiscal Note: The grant and resulting estimated reduction in annual energy costs of $2,100.00 will result in an 8 year return on investment.