File #: Res.06-6513    Version: A Name: AMENDMENT TO CONTRACT FOR LAKE MICHIGAN PATHWAY PHASE II
Type: Resolution Status: Passed
File created: 1/16/2006 In control: City Attorney's Office
On agenda: 1/17/2006 Final action: 1/17/2006
Title: AMENDMENT TO CONTRACT FOR LAKE MICHIGAN PATHWAY PHASE II

Sponsor

Alderman Engel

 

Title

AMENDMENT TO CONTRACT FOR LAKE MICHIGAN PATHWAY PHASE II

 

Body

RESOLVED, that Amendment No. 1 on Contract 1693-31-03, Lake Michigan Pathway, Phase II, Earth Tech, Inc., consultant, as submitted, be approved in the amount of $55,109.34.

 

FURTHER RESOLVED, that funding to defray the cost of these professional services be appropriated from Account 985.913.5080, Lakefront Bike Path, Phase II.

 

 

 