File #: Res.06-7062    Version: A Name: CHANGE ORDER LAKE MICHIGAN PATHWAY PHASE II
Type: Resolution Status: Passed
File created: 6/6/2006 In control: City Attorney's Office
On agenda: Final action: 6/6/2006
Title: CHANGE ORDER LAKE MICHIGAN PATHWAY PHASE II RESOLVED, that Change Order No. 1 on Contract 49-05 (K5-056, Lake Michigan Pathway Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $58,718.39. FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from the following accounts: $28,276.50 - Account 986.913.5080, Lake Michigan Pathway $27,812.96 - Account 731.000.5970, Kewaunee Street Demolition $ 2,628.93 - Account 104.985.5420, Storm Sewer, Various Locations $58,718.39 - Total FISCAL NOTE: Funds are available as herein delineated.
Sponsors: Ronald Hart
Related files: 06-1950

Sponsor

Alderman Hart

 

Title

CHANGE ORDER LAKE MICHIGAN PATHWAY PHASE II

 

 

RESOLVED, that Change Order No. 1 on Contract 49-05 (K5-056, Lake Michigan Pathway Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $58,718.39.

 

FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from the following accounts:

 

$28,276.50 - Account 986.913.5080, Lake Michigan Pathway

$27,812.96 - Account 731.000.5970, Kewaunee Street Demolition

$  2,628.93 - Account 104.985.5420, Storm Sewer, Various Locations

$58,718.39 - Total

 

 

FISCAL NOTE:  Funds are available as herein delineated.