File #: 0780-24    Version: A Name: Subject: Final Payment Request on Contract W-23-9, 2024 Water Main Replacement - Phase 2, Earth X LLC (contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-23-9 is complete at a final cost of $185,990.40.
Type: Communication Status: Passed
File created: 9/6/2024 In control: Waterworks Commission
On agenda: Final action: 9/17/2024
Title: Subject: Final Payment Request on Contract W-23-9, 2024 Water Main Replacement - Phase 2, Earth X LLC (contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-23-9 is complete at a final cost of $185,990.40.
Attachments: 1. w-23-9__2024 water main replacmt_final paymt req ltr to comsrs

Title

Subject: Final Payment Request on Contract W-23-9, 2024 Water Main Replacement - Phase 2, Earth X LLC (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract W-23-9 is complete at a final cost of $185,990.40.