Title: Change Order on contract Sixth Street Utility Construction Resolved, that Change Order No. 3 on Contract 3-08 (K8-003), Sixth Street Utility Construction, Globe Contractors, contractor, as submitted, be approved in the amount of $14,134.75. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $ 5,000.11 - Account 287.988.5310, Sanitary Sewer - Var. Loc. $ 7,188.64 - Account 104.988.5420, Storm Sewer - Var. Loc. $ 1,946.00 - Racine Water Utility $14,134.75 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 08-2253
Sponsor
Alderman Helding
 
Title
Change Order on contract Sixth Street Utility Construction
 
Resolved, that Change Order No. 3 on Contract 3-08 (K8-003), Sixth Street Utility Construction, Globe Contractors, contractor, as submitted, be approved in the amount of $14,134.75.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$  5,000.11 - Account 287.988.5310, Sanitary Sewer - Var. Loc.
$  7,188.64 - Account 104.988.5420, Storm Sewer - Var. Loc.
$  1,946.00 - Racine Water Utility
$14,134.75 - Total
 
 