Skip to main content
Ricine Banner
File #: 0053-26    Version: A Name: Subject: Consideration of Change Order No. 4 on Contract W-25-4, 2025 Lead Service Line Replacement, Miller Pipeline (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $94,130.33, bringing the contra
Type: Communication Status: Passed
File created: 1/15/2026 In control: Waterworks Commission
On agenda: Final action: 1/21/2026
Title: Subject: Consideration of Change Order No. 4 on Contract W-25-4, 2025 Lead Service Line Replacement, Miller Pipeline (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $94,130.33, bringing the contract total to $3,247,972.30.
Attachments: 1. CO#4_W-25-4

Title

Subject: Consideration of Change Order No. 4 on Contract W-25-4, 2025 Lead Service Line Replacement, Miller Pipeline (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in an increase of $94,130.33, bringing the contract total to $3,247,972.30.