Title:
|
Subject: Consideration of Change Order No. 4 on Contract W-25-4, 2025 Lead Service Line Replacement, Miller Pipeline (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in an increase of $94,130.33, bringing the contract total to $3,247,972.30.
|