Sponsor
Alderman Hart
Title
Change Order No. 2 on Contract to Upgrade Controls at Community Centers
Resolved, that Change Order No. 2 on Contract 44-06 (K6-047), Upgrade Temperature and HVAC Controls at Community Centers, Johnson Controls, Inc., contractor, as submitted, be approved in the amount of $13,659.00.
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
$ 3,198.00 - Account 987.650.5010, Humble Park Bldg Automation
$10,461.00 - Account 987.660.5010, MLK Center Bldg Automation
$13,659.00 - Total