Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 on Contract 44-06 (K6-047), Upgrade Temperature and HVAC Controls at Community Centers, Johnson Controls, Inc., contractor. Recommendation: That Change Order No. 2 on Contract 44-06 (K6-047), Upgrade Temperature and HVAC Controls at Community Centers, Johnson Controls, Inc., contractor, as submitted, be approved in the amount of $13,659.00. Further recommends that funding to defray the cost of this change order be appropriated from the following accounts: $ 3,198.00 - Account 987.650.5010, Humble Park Bldg Automation $10,461.00 - Account 987.660.5010, MLK Center Bldg Automation $13,659.00 - Total Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 44-06 CO #2.pdf
Related files: Res.07-0079
Title
Subject:  Direct Referral.  Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 on Contract 44-06 (K6-047), Upgrade Temperature and HVAC Controls at Community Centers, Johnson Controls, Inc., contractor.
 
Recommendation: That Change Order No. 2 on Contract 44-06 (K6-047), Upgrade Temperature and HVAC Controls at Community Centers, Johnson Controls, Inc., contractor, as submitted, be approved in the amount of $13,659.00.
 
Further recommends that funding to defray the cost of this change order be appropriated from the following accounts:
 
$  3,198.00 - Account 987.650.5010, Humble Park Bldg Automation
$10,461.00 - Account 987.660.5010, MLK Center Bldg Automation
$13,659.00 - Total
 